Work Profile Report [55W1982]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/262647/2024/PWD2-BUD/ANBU/21/2023-III-2-Public Works Department
TS Amount (lakhs) : 87.9 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
87.90
Resanction Cost :
87.90
Tentative Cost :
87.90
Exp. Upto Last Fy :
0.11
For CFY 2025-2026
Remaining :
87.79
Demand :
70.00
Allotment :
9.18
Exp in CFY :
9.18
Total Up to Date Exp :
9.29
Construction Started
Sanction on : 5 months 3 weeks ago
19 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
25 %
Tentative Completion date on : 8 months 2 weeks from now
28 Feb 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.40 कि0मी0 में कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 28-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand