Work Profile Report [55W1981]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/262647/2024/PWD2-BUD/ANBU/21/2023-III-2-Public Works Department
TS Amount (lakhs) : 38.85 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
38.85
Resanction Cost :
38.85
Tentative Cost :
38.85
Exp. Upto Last Fy :
0.09
For CFY 2025-2026
Remaining :
38.76
Demand :
30.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.09
Construction Started
Sanction on : 4 months 5 days ago
19 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
35 %
Up to Date :
50 %
Tentative Completion date on : 2 months 5 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.30 कि0मी0 में टाईल्स कार्य पूर्ण शेष कार्य प्रगति में है। -- as on 27-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: