Work Profile Report [55W1969]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/252131/2024/PWD2-BUD/ANBU/12/2023-III-2-Public Works Department
TS Amount (lakhs) : 79.95 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
79.95
Resanction Cost :
79.95
Tentative Cost :
79.95
Exp. Upto Last Fy :
23.86
For CFY 2025-2026
Remaining :
56.09
Demand :
50.00
Allotment :
4.08
Exp in CFY :
4.08
Total Up to Date Exp :
27.94
Construction Started
Sanction on : 7 months 2 days ago
07 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
80 %
Tentative Completion date on : 2 months 3 weeks from now
31 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.40 कि0मी0 में कार्य पूर्ण शेष कार्य प्रगति में है। -- as on 29-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: