Work Profile Report [55W1962]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/252131/2024/PWD2-BUD/ANBU/12/2023-III-2-Public Works Department
TS Amount (lakhs) : 75.99 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
75.99
Resanction Cost :
75.99
Tentative Cost :
75.99
Exp. Upto Last Fy :
26.07
For CFY 2025-2026
Remaining :
49.92
Demand :
35.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
26.07
Construction Started
Sanction on : 5 months 2 weeks ago
07 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
75 %
Tentative Completion date on : 3 months 6 days from now
31 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.90 कि0मी0 में टाईल्स कार्य पूर्ण शेष कार्य प्रगति में है। -- as on 27-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand