Administrative Approval Detail : 1/241293/2024/PWD2-BUD/ANBU/32/2023-III-2-Public Works Department
TS Amount (lakhs) : 51.16 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
51.16
Resanction Cost :
51.16
Tentative Cost :
51.16
Exp. Upto Last Fy :
16.65
For CFY 2025-2026
Remaining :
34.51
Demand :
32.04
Allotment :
17.04
Exp in CFY :
17.04
Total Up to Date Exp :
33.68
Work completed
Sanction on : 1 year 2 months ago
19 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
100 %
Tentative Completion date on : 6 months 11 hours ago
15 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण 07/2025 -- as on 30-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: