Work Profile Report [55W1948]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/239986/2024/PWD2-BUD/ANBU/32/2023-III-2-Public Works Department
TS Amount (lakhs) : 65.27 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
65.27
Resanction Cost :
65.27
Tentative Cost :
65.27
Exp. Upto Last Fy :
16.38
For CFY 2025-2026
Remaining :
48.89
Demand :
40.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
16.38
Construction Started
Sanction on : 7 months 1 week ago
13 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
50 %
Tentative Completion date on : 3 months 6 days from now
31 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
इंटरकोट तक कार्य पूर्ण, 1.00 कि0मी0 में टाॅपकोट तक कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 28-Feb-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: