Work Profile Report [55W1907]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/186272/2024/पीडब्लूडी2-बीयूडी/ एएनबीयू/36/2023-।।।-2-लो0नि0वि0
TS Amount (lakhs) : 69.67 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
69.67
Resanction Cost :
69.67
Tentative Cost :
69.67
Exp. Upto Last Fy :
36.33
For CFY 2025-2026
Remaining :
33.34
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
36.33
Work completed
Sanction on : 1 year 2 months ago
31 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 1 week ago
15 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण दायित्व शेष। -- as on 13-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: