Work Profile Report [54W1277]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 शासनादेश सं0-।/241387/2024 (पत्रावली संख्या-49305) लोक निर्माण अनुभाग-2, देहरादून, दिनांक 20.09.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
195.38
Resanction Cost :
195.38
Tentative Cost :
195.38
Exp. Upto Last Fy :
161.12
For CFY 2025-2026
Remaining :
34.26
Demand :
34.26
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
161.12
Work completed
Sanction on : 7 months 4 days ago
20 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 month 16 hours ago
24 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष है। -- as on 28-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: