Work Profile Report [54W1235]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 शासनादेश सं0-।/228568/2024 (ई पत्रावली संख्या-61203) लोक निर्माण अनुभाग-2, देहरादून, दिनांक 30.07.2024
TS Amount (lakhs) : 183.29 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
183.29
Resanction Cost :
183.29
Tentative Cost :
183.29
Exp. Upto Last Fy :
36.92
For CFY 2025-2026
Remaining :
146.37
Demand :
146.37
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
36.92
Construction Started
Sanction on : 8 months 3 weeks ago
30 Jul 2024
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 2 months 2 weeks from now
15 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
राफ्ट का कार्य पूर्ण। अन्य कार्य प्रगति पर है। -- as on 28-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand