Work Profile Report [54W1163]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 शा0सं0-।/111499/2023 (ई पत्रावली संख्या-49305), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 31.03.2023
TS Amount (lakhs) : 182.68 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
182.68
Resanction Cost :
182.68
Tentative Cost :
182.68
Exp. Upto Last Fy :
180.43
For CFY 2025-2026
Remaining :
2.25
Demand :
2.25
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
180.43
Construction Started
Sanction on : 2 years 3 weeks ago
31 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 10 months 6 days ago
18 Jun 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 02-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand