Work Profile Report [53W1756]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 46690 दिनांक 30.01.2025
TS Amount (lakhs) : 369.55 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
369.55
Resanction Cost :
369.55
Tentative Cost :
369.55
Exp. Upto Last Fy :
71.40
For CFY 2025-2026
Remaining :
298.15
Demand :
290.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
71.40
Construction Started
Sanction on : 2 months 3 weeks ago
30 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 11 months 6 days from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुबन्ध गठित कार्य प्रारम्भ किये जाने की कार्यवाही की जा रही है। -- as on 06-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand