Administrative Approval Detail : शासनादेश ई पत्रावली सं0 24012 दिनांक 27.01.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
119.96
Resanction Cost :
119.96
Tentative Cost :
119.96
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
119.96
Demand :
100.00
Allotment :
38.48
Exp in CFY :
38.48
Total Up to Date Exp :
38.48
Construction Started
Sanction on : 7 months 1 week ago
27 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
20 %
Tentative Completion date on : 6 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
नाली निर्माण का कार्य प्रगति पर है। (800 मी0) -- as on 02-Sep-2025