Work Profile Report [53W1703]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 24012/23 दिनांक 06.06.2024
TS Amount (lakhs) : 29.11 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
29.11
Resanction Cost :
29.11
Tentative Cost :
29.11
Exp. Upto Last Fy :
25.73
For CFY 2025-2026
Remaining :
3.38
Demand :
3.38
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
25.73
Work completed
Sanction on : 10 months 2 weeks ago
06 Jun 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date : 4 months 3 weeks ago
30 Nov 2024
Physical Linear Components
Remark
कार्य माह 11/24 में पूर्ण। -- as on 03-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: