Work Profile Report [53W1701]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेेश ई पत्रावली सं0 56385 दिनांक 15.03.2024
TS Amount (lakhs) : 67.68 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
67.68
Resanction Cost :
67.68
Tentative Cost :
67.68
Exp. Upto Last Fy :
50.50
For CFY 2025-2026
Remaining :
17.18
Demand :
17.18
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
50.50
Work completed
Sanction on : 1 year 1 month ago
15 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date : 3 weeks 3 days ago
31 Mar 2025
Physical Linear Components
Remark
कार्य माह 03/2025 में पूर्ण। -- as on 06-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: