Work Profile Report [53W1698]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 46690 दिनांक 15.03.2024
TS Amount (lakhs) : 157.18 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
157.18
Resanction Cost :
168.69
Tentative Cost :
168.69
Exp. Upto Last Fy :
110.97
For CFY 2025-2026
Remaining :
57.72
Demand :
46.21
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
110.97
Construction Started
Sanction on : 1 year 1 month ago
15 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 1 month 5 days from now
30 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
4.75 किमी0 लम्बाई में पहाड कटान का कार्य पूर्ण । अवशेष कार्य प्रगति पर है । -- as on 02-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: