Work Profile Report [52W521]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 ई0पत्रावली सख्या-38490 लोक निर्माण अनुभागं-2,देहरादून दिनांक 11 अगस्त 2023
TS Amount (lakhs) : 142.16 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
142.16
Resanction Cost :
142.16
Tentative Cost :
142.16
Exp. Upto Last Fy :
35.83
For CFY 2025-2026
Remaining :
106.33
Demand :
106.33
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
35.83
Construction Started
Sanction on : 1 year 8 months ago
11 Aug 2023
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
25 %
Tentative Completion date on : 3 months 3 weeks ago
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
1.750 कि 0 मी 0 पहाड़ कटान का कार्य पूर्ण| शेष कार्य प्रगति पर है। -- as on 27-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: