Work Profile Report [52W460]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 ई पत्रावली संख्या-48114 अनुभाग-2, देहरादून दिनांक 28.02.2023
TS Amount (lakhs) : 18 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
18.00
Resanction Cost :
18.00
Tentative Cost :
18.00
Exp. Upto Last Fy :
12.70
For CFY 2025-2026
Remaining :
5.30
Demand :
2.00
Allotment :
1.01
Exp in CFY :
0.73
Total Up to Date Exp :
13.43
Survey work done
Sanction on : 2 years 6 months ago
28 Feb 2023
Physical Progress:
At start of FY 2025-2026 :
70 %
Up to Date :
70 %
Tentative Completion date on : 11 months 1 week ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ई0डी.पी.आर. की खण्डीय स्तर पर जांच की जा रही है। -- as on 05-Sep-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: