Work Profile Report [52W365]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-5299/।।।(2)/18-37(प्रा0आ0)/2013 दिनांक 31.10.2018 द्वारा रू0 332.72 लाख की स्वीकृति प्राप्त।
TS Amount (lakhs) : 332.72 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
332.72
Resanction Cost :
332.72
Tentative Cost :
332.72
Exp. Upto Last Fy :
327.45
For CFY 2025-2026
Remaining :
5.27
Demand :
5.27
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
327.45
Work completed
Sanction on : 6 years 5 months ago
31 Oct 2018
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 years 3 weeks ago
31 Mar 2021
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
माह 03/2021 में कार्य पूर्ण,दायित्वों का भुगतान शेष। -- as on 01-Sep-2021
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand