Work Profile Report [52W34]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-1754/111-2/5-64 (प्रा0आ0)/05 दि0 10.11.2005
TS Amount (lakhs) : 198.7 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
198.70
Resanction Cost :
562.53
Tentative Cost :
562.53
Exp. Upto Last Fy :
383.53
For CFY 2025-2026
Remaining :
179.00
Demand :
179.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
383.53
Work completed
Sanction on : 19 years 5 months ago
10 Nov 2005
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
50 %
Tentative Completion date on : 2 months 5 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 08-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: