Work Profile Report [52W32]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-2658/111-2/06-17 (प्रा0आ0)/06 दि0 25.09.2006
TS Amount (lakhs) : 147.56 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
56.70
Resanction Cost :
73.78
Tentative Cost :
73.78
Exp. Upto Last Fy :
68.72
For CFY 2025-2026
Remaining :
5.06
Demand :
5.06
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
68.72
Work completed
Sanction on : 18 years 6 months ago
25 Sep 2006
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 months 3 weeks ago
31 Jan 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का 3.50 कि.मी. कार्य माह 05/2023 को पूर्ण, प्रतिकर पत्रावली गठित कर अनुुमोदन पश्चात प्रतिकर वितरण कर दिया जायेगा। -- as on 08-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: