Work Profile Report [51W172]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. 1377/।।।(2)/09-24(मा.मु.मं.घो.)/09 टी.सी.-1 दि. 23.3.2010
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
663.06
Resanction Cost :
663.06
Tentative Cost :
663.06
Exp. Upto Last Fy :
610.27
For CFY 2025-2026
Remaining :
52.79
Demand :
45.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
610.27
Construction Started
Sanction on : 15 years 1 month ago
23 Mar 2010
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
90 %
Tentative Completion date on : 2 months 5 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
90% work completed -- as on 22-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: