Work Profile Report [51W1174]

एस0डी0एम0एफ0 वर्ष 2022-23 के अन्तर्गत मालदेवता - सेरकी - सिल्ला मोटर मार्ग को भूस्खलन से बचाने हेतु सुरक्षात्मक कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : ENC letter No 5455/79 Budget (SDMF)/2022-23 Dt. 29.3.23

TS Amount (lakhs) : 225.25 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

225.25

Resanction Cost :

225.25

Tentative Cost :

225.25

Exp. Upto Last Fy :

90.00

For CFY 2025-2026

Remaining :

135.25

Demand :

135.25

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

90.00

Construction Started

Sanction on : 2 years 3 weeks ago

29 Mar 2023

Physical Progress:

At start of FY 2025-2026 :

60 %

Up to Date :

60 %

Tentative Completion date on : 8 months 3 weeks ago

31 Jul 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Jobs
1
1
0
1
0
0

Remark

view all

कार्य माह जून 2023 मे प्रारंभ कर दिया गया था ,विगत बर्षात मे बाँदल नदी मे आई अतिवृष्टि के कारण कृत कार्य का आंशिक भाग क्षतिग्रस्त होने तथा कार्यस्थल की भौगोलिक स्थिति मे भारी परिवर्तन ( अधिक कटाव ) होने के कारण पूर्व स्वीकृत आगणन के प्रविधानों के अनुरूप कार्य कराया जाना संभव नहीं है। उपलब्ध धनराशि से करवाए जाने वाले परिवर्तित कार्यों का प्रस्ताव मुख्य अभियंता देहरादून से स्वीकृत होने के उपरांत कार्य पूर्ण कर लिये गये हैं जिनके भुगतान हेतु द्वितीय किस्त की धनराशि की मांग हेतु प्रपत्र उच्चाधिकारियों को प्रस्तुत हैं। वर्तमान मे इस मार्ग पर सुदरीकरण कार्य पी0एम0जी0एस0वाई0 के अधीन स्वीकृत हो चुका है। -- as on 07-Dec-2024

Rating : 60

No Forest Case in The Work

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI: