Work Profile Report [4W2]

सुनोली-दड़माड़ मोटर मार्ग ।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनादेश सं. 112/लो.नि.-2/ 04- 04 (प्रा.आ.)/04 दि0 6.2.04

TS Amount (lakhs) : 48.65 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

48.65

Resanction Cost :

48.65

Tentative Cost :

48.65

Exp. Upto Last Fy :

38.42

For CFY 2025-2026

Remaining :

10.23

Demand :

5.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

38.42

Work completed

Sanction on : 21 years 2 months ago

06 Feb 2004

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 10 years 3 weeks ago

31 Mar 2015

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3.5
3.5
3.500
0
0.000
0.000

Remark

view all

कार्य पूर्ण।मुआवजे के प्रपत्र गठित। मुआवजे का भुगतान शेष। -- as on 31-Jul-2020

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: