Work Profile Report [4W152]

रानीखेत-गगास मोटर मार्ग ।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Nabard
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनदेश सं.288/लो.नि.-2-04 -15 (प्रा.आ.)/ 04 दि. 27.2.04

TS Amount (lakhs) : 94.2 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

94.20

Resanction Cost :

94.20

Tentative Cost :

83.48

Saving

10.72

Exp. Upto Last Fy :

83.48

For CFY 2025-2026

Remaining :

10.72

Demand :

10.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

83.48

Work completed

Sanction on : 21 years 1 month ago

27 Feb 2004

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 5 years 3 weeks ago

31 Mar 2020

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
6
6
6.000
0
0.000
0.000

Remark

view all

Overall Saving 10.72 has been recorded as expected cost of work reduced from 94.2 to 83.48 . कार्य पूर्ण। -- as on 25-Nov-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand