Work Profile Report [49W631]

नैनबाग ऐन्दी मोटर मार्ग के किमी० 22 में क्षतिग्रस्त दीवार का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : DM letter 22/VIII-जि०यो० -09/2024-25 दिनांक 26-07-2024

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

4.50

Resanction Cost :

4.50

Tentative Cost :

4.50

Exp. Upto Last Fy :

3.00

For CFY 2025-2026

Remaining :

1.50

Demand :

1.50

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

3.00

Work completed

Sanction on : 8 months 4 weeks ago

26 Jul 2024

Physical Progress:

At start of FY 2025-2026 :

70 %

Up to Date :

100 %

Tentative Completion date on : 1 month 2 weeks ago

04 Mar 2025

Actual Completion Date : 3 weeks 16 hours ago

03 Apr 2025

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

कार्य पूर्ण, वित्तीय दायित्व शेष | -- as on 04-Mar-2025

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: