Work Profile Report [49W447]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 1702(1)/।।।(2)21-48(प्रा0आ0)/2018 दिनांक 16.06.2021
TS Amount (lakhs) : 78.2 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
78.20
Resanction Cost :
78.20
Tentative Cost :
78.20
Exp. Upto Last Fy :
4.71
For CFY 2025-2026
Remaining :
73.49
Demand :
40.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
4.71
Alignment Approved
Sanction on : 3 years 10 months ago
16 Jun 2021
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
20 %
Tentative Completion date on : 11 months 6 days from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
संरेखण विवाद , जिसे सुलझाने का प्रयास किया जा रहा है | -- as on 04-Jan-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: