Administrative Approval Detail : शासनादेश सं0 1342/।।। (2)/21-25 (प्रा0आ)/2017 टी0सी0-।। दिनांक 13.05.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
76.89
Resanction Cost :
76.89
Tentative Cost :
76.89
Exp. Upto Last Fy :
67.72
For CFY 2025-2026
Remaining :
9.17
Demand :
9.17
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
67.72
Work completed
Sanction on : 3 years 11 months ago
13 May 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 6 months ago
30 Sep 2023
Actual Completion Date : 1 year 6 months ago
30 Sep 2023
Physical Linear Components
Remark
कार्य पूर्ण,दायित्वो का भुगतान शेष । -- as on 25-Dec-2024
Assets :
Work not linked with IM