Work Profile Report [49W388]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ष्शा0 सं0 557(1)/।।।(2)/20-25 (प्रा0आ0)/2017, दि0 05.02.2020
TS Amount (lakhs) : 1007.07 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1007.07
Resanction Cost :
1007.07
Tentative Cost :
1007.07
Exp. Upto Last Fy :
1,006.62
For CFY 2025-2026
Remaining :
0.45
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1,006.62
In Maintenance After Completion
Sanction on : 5 years 4 months ago
05 Feb 2020
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 2 weeks ago
12 Jun 2024
Actual Completion Date : 1 year 2 weeks ago
12 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 02-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: