Work Profile Report [49W318]
Fin Plan
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0-518(1)/एक्स वी0 ।।।(1)/18-01(11)/17 दि0 24.03.2018
TS Amount (lakhs) : 14.05 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
14.05
Resanction Cost :
14.05
Tentative Cost :
14.05
Exp. Upto Last Fy :
3.82
For CFY 2025-2026
Remaining :
10.23
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
3.82
Phase1 DPR Submitted
Sanction on : 7 years 3 months ago
24 Mar 2018
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 2 months 4 weeks ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम चरण का कार्य पूर्ण, वित्तीय दायित्व शेष | द्वितीय चरण की स्वीकृति प्राप्त। -- as on 27-Nov-2024
Assets :
Work not linked with IM