Work Profile Report [49W22]
Tenders
Project Activities
alerts
Administrative Approval Detail : शा0स0 1960/111-/08-09(एम0एल0ए0)/07 दिनाॅक 26.06.2008
TS Amount (lakhs) : 398.91 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
490.60
Resanction Cost :
490.60
Tentative Cost :
490.60
Exp. Upto Last Fy :
480.73
For CFY 2025-2026
Remaining :
9.87
Demand :
9.87
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
480.73
Work completed
Sanction on : 16 years 9 months ago
26 Jun 2008
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date : 4 months 4 weeks ago
26 Nov 2024
Physical Linear Components
Remark
कार्य पूर्ण , वित्तीय दायित्व शेष | -- as on 26-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: