Work Profile Report [49W205]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0-1868/।।।(2)/16-19(प्रा0आ0)/2016 दिनाॅक-07.06.2016
TS Amount (lakhs) : 160.06 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
160.06
Resanction Cost :
160.06
Tentative Cost :
160.06
Exp. Upto Last Fy :
117.59
For CFY 2025-2026
Remaining :
42.47
Demand :
42.47
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
117.59
Construction Started
Sanction on : 8 years 10 months ago
07 Jun 2016
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on : 3 months 6 days from now
31 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का कार्य पूर्ण | पार्ट -2 के अंतर्गत दीवार का कार्य लगभग 50% एवं कल्वर्ट निर्माण का कार्य प्रगति पर | -- as on 27-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: