Work Profile Report [49W203]
Tenders
Project Activities
alerts
Administrative Approval Detail : 1868/।।।(2)/16-19(प्रा0आ0)/2016 दिनाॅक-7 जून 2016
TS Amount (lakhs) : 258 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
258.00
Resanction Cost :
258.00
Tentative Cost :
258.00
Exp. Upto Last Fy :
172.90
For CFY 2025-2026
Remaining :
85.10
Demand :
84.81
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
172.90
Construction Started
Sanction on : 8 years 10 months ago
07 Jun 2016
Physical Progress:
At start of FY 2025-2026 :
70 %
Up to Date :
70 %
Tentative Completion date on : 10 months 3 days from now
28 Feb 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पार्ट-2 का कार्य 3.50 किमी० लम्बाई में पूर्ण | वर्तमान में 12 मीटर स्पान हेतु सेतु कार्य प्रगति पर | -- as on 10-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: