Work Profile Report [47W556]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : DM-Tehri Ltr No-161/-Jio-2017-18 Date 09.05.2018
TS Amount (lakhs) : 35.9 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
35.90
Resanction Cost :
35.90
Tentative Cost :
35.90
Exp. Upto Last Fy :
28.41
For CFY 2025-2026
Remaining :
7.49
Demand :
7.49
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
28.41
Work completed
Sanction on : 6 years 11 months ago
09 May 2018
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 weeks ago
31 Mar 2024
Actual Completion Date : 9 months 3 weeks ago
30 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष। -- as on 24-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand