Work Profile Report [47W196]

fलंगवाणा से सौड़ू रानीताल से मोल्टा मोटर मार्ग का नवfनर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

  • Project Activities
  • alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0 सं0 549/।।।(2)/14-49(प्रा0आ0)/2013 दि0 29.01.2014

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

79.50

Resanction Cost :

79.50

Tentative Cost :

79.50

Exp. Upto Last Fy :

11.99

For CFY 2025-2026

Remaining :

67.51

Demand :

30.00

Allotment :

7.00

Exp in CFY :

2.58

Total Up to Date Exp :

14.57

Alignment Approved

Sanction on : 11 years 4 months ago

29 Jan 2014

Physical Progress:

At start of FY 2025-2026 :

30 %

Up to Date :

30 %

Tentative Completion date on : 9 months 3 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
4.15
0.000
4.15
4.150
0.000

Remark

view all

प्रकरण विधिवत स्वीकृति हेतु भारत सरकार स्तर पर लम्बित है। भूमि प्रतिकर गठित। प्रतिकर वितरण की कार्यवाही गतिमान। -- as on 04-Jun-2025

Rating : 35

Forest Case Pending At : 17: AIP Govt of India

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: