Work Profile Report [46W615]
Tenders
Project Activities
Samples
Administrative Approval Detail : उत्तराखण्ड शासन देहरादून का ई पत्रावली संख्या-30972 लोक निर्माण अनुभाग-2 देहरादून दिनांक 12 अक्टूबर 2023
TS Amount (lakhs) : 414.39 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
414.39
Resanction Cost :
414.39
Tentative Cost :
414.39
Exp. Upto Last Fy :
369.32
For CFY 2025-2026
Remaining :
45.07
Demand :
32.24
Allotment :
32.24
Exp in CFY :
9.99
Total Up to Date Exp :
379.31
Work completed
Sanction on : 1 year 7 months ago
12 Oct 2023
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
100 %
Tentative Completion date on : 1 month 1 week ago
30 Apr 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण । -- as on 06-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: