Work Profile Report [45W173]

घनसाली-कोटी-अखोड़ी मोटर मार्ग के कि0मी0-13 (बांझगला) से अरोली-पंतवालगावं-सिल्ला-जाख तक मोटर मार्ग का निव निर्माण कार्य। (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 451/।।।(2)/20-09(एम0एल0ए0)/2017 टी0सी0, दिनांक 28.01.2020

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

15.52

Resanction Cost :

15.52

Tentative Cost :

15.52

Exp. Upto Last Fy :

1.01

For CFY 2025-2026

Remaining :

14.51

Demand :

0.50

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1.01

Alignment Approved

Sanction on : 5 years 2 months ago

28 Jan 2020

Physical Progress:

At start of FY 2025-2026 :

5 %

Up to Date :

5 %

Tentative Completion date on : 11 months 6 days from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
4
0
0.000
0
0.000
0.000

Remark

view all

प्रभागीय वनाधिकारी, टिहरी वनप्रभाग, नई टिहरी से वनभूमि पत्रावली प्राप्त कर कार्यालय जिलाधिकारी, टिहरी गढवाल को प्रतिहस्ताक्षर करनेहतु अधिशासी अभियन्ता के पत्रांक- 448/10एम0जी0, दिनांक- 21.04.2025 को प्रेषित। -- as on 23-Apr-2025

Rating : 9

Forest Case Pending At : 04: DFO

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: