Work Profile Report [45W102]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं 6667/।।।(2)/13-32(प्रा0आ0)/2013 दिनांक 22.11.2013
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
49.95
Resanction Cost :
49.95
Tentative Cost :
20.00
Saving
29.95
Exp. Upto Last Fy :
19.03
For CFY 2025-2026
Remaining :
30.92
Demand :
0.97
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
19.03
Work completed
Sanction on : 11 years 5 months ago
22 Nov 2013
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 3 weeks 4 days ago
30 Mar 2025
Actual Completion Date : 3 weeks 4 days ago
30 Mar 2025
Physical Linear Components
Remark
Overall Saving 29.95 has been recorded as expected cost of work reduced from 49.95 to 20.00 . -- as on 11-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: