Work Profile Report [44W630]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश संख्या-4990(1)/।।।(2)/21-39 (प्रा0आ0)/2018 दिनंाक 22 अक्टूबर, 2021
TS Amount (lakhs) : 489.89 Lacs
Budget Financial Head : Building ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
489.89
Resanction Cost :
489.89
Tentative Cost :
412.38
Saving
77.51
Exp. Upto Last Fy :
291.05
For CFY 2025-2026
Remaining :
198.84
Demand :
120.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
291.05
Construction Started
Sanction on : 3 years 6 months ago
22 Oct 2021
Physical Progress:
At start of FY 2025-2026 :
65 %
Up to Date :
65 %
Tentative Completion date on : 1 month 3 weeks ago
28 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 77.51 has been recorded as expected cost of work reduced from 489.89 to 412.38 . -- as on 09-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand