Work Profile Report [43W976]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 1488/111/2/20-13 /एम0एल0ए0/ 2017 TC दि0 14/08/2020
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
243.53
Resanction Cost :
243.53
Tentative Cost :
243.53
Exp. Upto Last Fy :
158.96
For CFY 2025-2026
Remaining :
84.57
Demand :
25.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
158.96
Construction Started
Sanction on : 4 years 5 months ago
18 Nov 2020
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 7 months 5 days from now
30 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
T beam slab bridge work in progress. -- as on 12-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: