Work Profile Report [43W464]

जनपद टिहरी गढ़वाल के विधानसभा क्षेत्र प्रतापनगर के अन्तर्गत कण्डियालगांव से दिन्याली देवी मो0 मार्ग का निर्माण कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0 सं0 4531/111(2)/15-13(प्रा0आ0)/2015 दि0 05.06.2015

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

50.85

Resanction Cost :

50.85

Tentative Cost :

50.85

Exp. Upto Last Fy :

28.82

For CFY 2025-2026

Remaining :

22.03

Demand :

20.03

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

28.82

Phase1 DPR Submitted

Sanction on : 9 years 10 months ago

05 Jun 2015

Physical Progress:

At start of FY 2025-2026 :

56 %

Up to Date :

56 %

Tentative Completion date on : 11 months 6 days from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
5
3.6
3.6
-

Remark

view all

प्रतिकर पत्रावली तहसील स्तर से सत्यापित हो गयी है। स्वीकृत प्रतिकर भुगतान की कार्यवाही प्रगति पर । -- as on 08-Apr-2025

Rating : 69

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: