Work Profile Report [43W216]

जनपद टिहरी गढ़वाल के प्रतापनगर में सिलोली नामे तोक से हितैडु खाण्ड (धारमण्डल) तक मोटर मार्ग क निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0 5527/।।।(2)/10-04(एम0एल0ए0)/2010 दि0 13/12/2011

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

37.80

Resanction Cost :

37.80

Tentative Cost :

15.00

Saving

22.80

Exp. Upto Last Fy :

0.98

For CFY 2025-2026

Remaining :

36.82

Demand :

10.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.98

Phase1 DPR Submitted

Sanction on : 14 years 4 months ago

13 Dec 2010

Physical Progress:

At start of FY 2025-2026 :

25 %

Up to Date :

25 %

Tentative Completion date on : 4 months 5 days from now

30 Aug 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
0
0
-

Remark

view all

अधी0 अभि0 के पत्रांक 3265/668सी-8/2024 दि0 03.12.2024 द्वारा समरेखण स्वीकृत। परंतु ग्रामीणों द्वारा विवाद किया जा रहा है, विवाद सुलझाने का प्रयास किया जा रहा है । -- as on 12-Apr-2025

Rating : 26

No Forest Case in The Work

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI: