Work Profile Report [43W1080]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : e file 74390 dt 19-12-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
191.52
Resanction Cost :
191.52
Tentative Cost :
191.52
Exp. Upto Last Fy :
2.96
For CFY 2025-2026
Remaining :
188.56
Demand :
75.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.96
Construction Started
Sanction on : 4 months 6 days ago
18 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
40 %
Tentative Completion date on : 4 months 5 days from now
30 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
02 किमी लंबाई में पहाड़ कटान का कार्य पूर्ण , अवशेष भाग में पहाड़ कटान का कार्य प्रगति पर है। -- as on 12-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: