Work Profile Report [43W1079]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : e file 51381 dt 02-01-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
171.68
Resanction Cost :
171.68
Tentative Cost :
171.68
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
171.58
Demand :
171.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Construction Started
Sanction on : 3 months 3 weeks ago
02 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 6 months 5 days from now
30 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर । -- as on 24-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand