Work Profile Report [43W1074]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : e file 56385 dt 06-11-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
288.77
Resanction Cost :
288.77
Tentative Cost :
288.77
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
288.77
Demand :
234.67
Allotment :
2.00
Exp in CFY :
0.25
Total Up to Date Exp :
0.25
Construction Started
Sanction on : 7 months 3 days ago
06 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 1 month 5 days from now
15 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रारंभ -- as on 25-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: