Work Profile Report [43W1071]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : e file 56385 dt 06-11-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
614.78
Resanction Cost :
614.78
Tentative Cost :
614.78
Exp. Upto Last Fy :
553.00
For CFY 2025-2026
Remaining :
61.78
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
553.00
Construction Started
Sanction on : 5 months 2 weeks ago
06 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 2 months 5 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
क्रैश बैरियर कार्य प्रगति पर । -- as on 04-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: