Work Profile Report [43W1034]
Tenders
Project Activities
Samples
Administrative Approval Detail : e file 36639/12 dt 10-01-2024
TS Amount (lakhs) : 143.18 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
143.18
Resanction Cost :
143.18
Tentative Cost :
143.18
Exp. Upto Last Fy :
137.08
For CFY 2025-2026
Remaining :
6.10
Demand :
1.13
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
137.08
In Maintenance After Completion
Sanction on : 1 year 3 months ago
10 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 months 3 weeks ago
31 Jan 2025
Actual Completion Date : 5 months 3 weeks ago
31 Oct 2024
Physical Linear Components
Remark
प्रथम वर्ष का अनुरक्षण कार्य पूर्ण । -- as on 02-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand