Administrative Approval Detail : ई-फाईल संख्या 50637/140131/2023 दिनंाक 24-7-2023
TS Amount (lakhs) : 470.35 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
470.35
Resanction Cost :
470.35
Tentative Cost :
470.35
Exp. Upto Last Fy :
456.93
For CFY 2025-2026
Remaining :
13.42
Demand :
13.41
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
456.93
Construction Started
Sanction on : 1 year 9 months ago
24 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 1 week 4 days ago
13 Apr 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान, स्कपर निर्माण, दीवार निर्माण , रोड सेफ्टी कार्य , जी0-1 , जी0-2 , जी0-3 एवं पी0सी0 द्वारा डामरीकरण का कार्य पूर्ण । -- as on 02-Apr-2025
Assets :