Work Profile Report [40W10]

मदमहेश्वर घाटी के अन्तर्गत तलसारी तोक से गौण्डार तक मोटर मार्ग का नव निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 2847(1)।।।-2/05-79प्रा0आ0/05 दि0 19.12.05

TS Amount (lakhs) : 249.1 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

84.00

Resanction Cost :

249.10

Tentative Cost :

249.10

Exp. Upto Last Fy :

112.60

For CFY 2025-2026

Remaining :

136.50

Demand :

35.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

112.60

Construction Started

Sanction on : 19 years 4 months ago

19 Dec 2005

Physical Progress:

At start of FY 2025-2026 :

35 %

Up to Date :

35 %

Tentative Completion date on : 1 month 6 days from now

31 May 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
5
5
0.000
5
1.000
0.000

Remark

view all

स्वीकृत लम्बाई 5.00 किमी0 के सापेक्ष 2.00 किमी0 लम्बाई में पहाड कटान का कार्य पूर्ण। कि॰मी॰ 3 में पहाड कटान का कार्य प्रगति पर। कटिंग साइट चट्टानी तथा वर्टीकल होने से व इस मार्ग के नीचे मस्ता मदमहेश्वर पैदल मार्ग है यात्राकाल में कटिंग का कार्य बन्द रहता है जिस कारण पहाट कटान का कार्य नही किया जा पा रहा है। -- as on 18-Apr-2025

Rating : 46

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: