Work Profile Report [3W697]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : E File No 56049
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
49.81
Resanction Cost :
49.81
Tentative Cost :
49.81
Exp. Upto Last Fy :
24.84
For CFY 2025-2026
Remaining :
24.97
Demand :
5.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
24.84
Work completed
Sanction on : 1 year 8 months ago
27 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 01-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand