Administrative Approval Detail : 5315/III(2)/21-49(MLA)/2017 TC
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1129.73
Resanction Cost :
1427.35
Tentative Cost :
1427.35
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
1,427.25
Demand :
400.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Unstarted Work
Sanction on : 3 years 5 months ago
02 Nov 2021
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 1 year 11 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 297.62 has been counted as tentative cost increased from 1129.73 to 1427.35 . -- as on 04-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: